• Interior Project by Broadfield Customs Part II

    More finishing work continues on the trim pieces. Ultra-thin coat of pinhole filler: Blocked down with 180-Grit: A texture coating and then blocked down again for referencing: One more time to get it perfectly straight: Final texture coat, waiting on the color topcoat now: It is nice to witness all of the shavings and fillings […]

    5 responses August 6, 2015
  • Interior Project by Broadfield Customs

    At long last, I’m back with an update. Over the past couple of years, I’ve been able to maintain a high cadence in terms of modifications and progress. Things are now culminating to a finale by way of brute productivity and will. I no longer have the time nor the facilities these days to continue […]

    One response August 5, 2015
  • Fine-Tunes and Tweaks

    I dropped the RX-7 back to Marcus Fry Racing Enterprises to tackle the aforementioned adjustments and bug fixes, and get the running condition to be perfect. In a twist of irony, you can start to feel complacent after undertaking a large project like the LS3 swap… the initial motivation starts to wane. However, all the […]

    5 responses June 22, 2015
  • ’99 Spoiler with Odula Insert

    The Shine FEED Type II spoiler that has been on the car for the past 2 years served its use well, but it is time to expand towards bolder directions. Since I had the ’99 front bumper installed for the third time, I decided to maintain a congruency at the rear as well with a ’99 […]

    One response November 10, 2014
  • Clutch Fix and Alignment

    Attempts were made to re-bleed the clutch but its behavior started to become increasingly erratic. Instead of having the clutch pedal gradually fall to the floor, it would randomly fall to the floor and then come back up. The usual pattern was no longer observable, which disproved the theory of an air bubble expanding with […]

    No responses November 10, 2014
  • Week Seventeen

    Work was measurably amped up during the past couple of weeks to push this swap through the finish line. Once the engine was started and running, attention was turned to ironing out all the minor bugs and any drivability issues. Marcus spent a good deal of time locating and silencing noises and making sure the […]

    No responses November 4, 2014
  • Week Sixteen

    With the exhaust fabricated, attention has turned to finishing up the wiring and mounting the battery box. Marcus also redid the intake piping that came with the Samberg radiator kit and its LS7/LS3 MAF adapter. The fitment of this pipe puts it close to the hood with the LS3’s drive-by-wire throttle body, so the goal […]

    One response October 25, 2014
  • Week Fifteen

    FINALLY, progress. The car has admittedly been sitting mostly idle inside the shop while other matters came up. Marcus is in the process of opening another, larger shop and has likely been spending most of his time there setting it up. I know extended wait times come with the territory with these large scale projects, […]

    One response October 20, 2014
  • Weeks Ten to Twelve

    Although the car is taking longer than initially expected to finish, the passing time has given me a new perspective. I can’t hide the fact that I’m anxious to have the swap completed, but at the same time I’m comforted by having the luxury of busying myself with other aspects of life while the work […]

    5 responses September 29, 2014
  • Weeks Eight to Nine

    As the weeks slide by, I can feel my anticipations and anxieties starting to swell. I am having to consciously suppress images of myself terrorizing the streets of the Bay Area with tire smoking abandon, for that time is not yet ready. Nonetheless, progress can’t be rushed and the waiting should hopefully help make the […]

    One response September 8, 2014
  • Weeks Six to Seven

    Both the front subframe/engine and rear subframe/differential are installed. Work is now focusing on the smaller items on the to-do list. This portion is all detail-oriented and deservedly requires the most time due to its inherent tediousness. Here is a snippet of some of the progress that has been recently made, as this swap creeps […]

    One response August 26, 2014
  • Week Five

    Getting close! All the major parts are in, like this custom length aluminum 3.5″ driveshaft from none other than The Driveshaft Shop. We had to place priority on getting the front and rear subframes prepared and ready for mock up in order to take the measurement for the driveshaft. I then placed the order immediately […]

    2 responses August 8, 2014